Multiple Choice Identify the
choice that best completes the statement or answers the question.
|
|
|
1.
|
All of the following are metrics of a successful project EXCEPT ____.
a. | on-time completion | b. | completion with the same personnel as were on
the team at the outset | c. | completion within budget | d. | delivery of a
quality product that satisfies users |
|
|
|
2.
|
A project manager’s scheduling function _____.
a. | involves guiding, supervising, and coordinating the project team’s
workload | b. | includes monitoring the progress of the project, evaluating results, and taking
corrective action when necessary to stay on target | c. | involves staffing, which includes selecting the
project team and assigning specific tasks to team members | d. | includes identifying
and arranging project tasks and estimating completion times and costs |
|
|
|
3.
|
Project scheduling involves all of the following EXCEPT ____.
a. | defining project constraints | c. | using Gantt
charts | b. | staffing the project team | d. | assigning specific tasks to team members |
|
|
|
4.
|
The accompanying figure shows task ____, which simplify a complex task by
combining several activities.
a. | groups | c. | aggregates | b. | clusters | d. | links |
|
|
|
5.
|
Many project managers find ____ charts more helpful for scheduling, monitoring,
and controlling projects.
a. | Gantt | c. | index | b. | PERT/CPM | d. | task |
|
|
|
6.
|
A(n) ____ chart displays complex task patterns and relationships.
a. | Gantt | c. | PERT/CPM | b. | index | d. | task |
|
|
|
7.
|
A task is any work that requires the use of company resources including all of
the following EXCEPT ____.
a. | controlling capital | c. | time | b. | people | d. | money |
|
|
|
8.
|
In addition to tasks, every project has ____, which are reference points used to
monitor progress and manage the project.
a. | targets | c. | members | b. | milestones | d. | workloads |
|
|
|
9.
|
In a PERT/CPM chart, each task has all of the following EXCEPT a(n) ____.
a. | reference to successor tasks | c. | name | b. | ID | d. | duration |
|
|
|
10.
|
When several tasks can start at the same time, each is called a(n) ____
task.
a. | synchronous | c. | baseline | b. | asynchronous | d. | concurrent |
|
|
|
11.
|
When two or more concurrent tasks depend on a single prior task, the concurrent
tasks are called ____ tasks.
a. | descendent | c. | children | b. | successor | d. | antecedent |
|
|
|
12.
|
A ____ path includes all tasks that are vital to the project schedule.
a. | vital | c. | critical | b. | baseline | d. | foundational |
|
|
|
13.
|
Project managers always must be aware of the ____ path, so they can monitor the
vital tasks and keep the project on track.
a. | vital | c. | foundational | b. | baseline | d. | critical |
|
|
|
14.
|
When maintaining schedules, if enough ____ and frequent checkpoints exist,
problems will be detected rapidly.
a. | success indices | c. | milestones | b. | critical paths | d. | all of the
above |
|
|
|
15.
|
____ is open-source software that is supported by a large group of users and
developers.
a. | Open Workbench | c. | Microsoft Project Professional | b. | Microsoft Project
Standard | d. | Both b and
c |
|
|
|
16.
|
A _____ cannot be started until one or more other tasks are completed.
a. | dependent task | c. | predecessor task | b. | concurrent task | d. | all of the
above |
|
|
|
17.
|
A ____ is an event that could affect a project negatively.
a. | menace | c. | doubt | b. | threat | d. | risk |
|
|
|
18.
|
A(n) ____ chart can be used to display the qualitative risk analysis
matrix.
|
|
|
19.
|
When an information system does not meet business requirements, causes might
include ____.
a. | unidentified requirements | c. | imprecise
targets | b. | inadequately defined scope | d. | all of the above |
|
|
|
20.
|
All of the following are possible causes of cost overruns related to human
resource factors EXCEPT ____.
a. | motivation issues | c. | inaccurate TCO forecast | b. | inadequate
training | d. | turnover |
|
|
|
21.
|
When a project manager first recognizes that a project is in trouble, the
options available to her include ____.
a. | trimming the project requirements | c. | adding to the project
resources | b. | delaying the project deadline | d. | all of the
above |
|
True/False Indicate whether the
statement is true or false.
|
|
|
22.
|
Gantt charts are an ideal tool for controlling a complex project because they
provide plenty of detailed information.
|
|
|
23.
|
If it will take one person 20 days to perform a particular task, it is true that
two people could complete the same task in 10 days or that 10 people could perform the task in two
days.
|
|
|
24.
|
In most systems analysis tasks, time and people are interchangeable.
|
|
|
25.
|
Using prior experience to make time and cost estimates works best for large
projects.
|
|
|
26.
|
When tasks must be completed one after another, they are called concurrent
tasks.
|
|
|
27.
|
Often, two or more concurrent tasks depend on a single prior task, which is
called a successor task.
|
|
|
28.
|
When two or more concurrent tasks depend on a single prior task, each of the
concurrent tasks is called a predecessor task.
|
|
|
29.
|
If any task along the critical path falls behind schedule, the entire project is
delayed.
|
|
|
30.
|
Generally, systems analysts review the work of other systems analysts, and
programmers review the work of other programmers, as a form of peer review, in structured
walk-throughs.
|
|
|
31.
|
Tasks that are not on the critical path cannot be ignored.
|
|
|
32.
|
In Open Workbench, unlike in Microsoft Project, you create tasks and durations,
indicate dependencies, and assign resources.
|
|
|
33.
|
Project planning is a dynamic task and involves constant change.
|
|
|
34.
|
If team members lack experience with certain aspects of the required technology,
temporary help might be obtained from IT consultants or part-time staff.
|
Completion Complete each
statement.
|
|
|
35.
|
The ____________________ handles administrative responsibilities for a project
development team and negotiates with users who might have conflicting requirements or want changes
that would require additional time or expense.
|
|
|
36.
|
A(n) ____________________ is a recognizable reference point that can be used to
monitor progress and manage a project.
|
|
|
37.
|
A(n) ____________________ represents the amount of work that one person can
complete in one day.
|
|
|
38.
|
The ____________________ is the time that a task is scheduled to begin.
|
|
|
39.
|
The ____________________ is the time that a task is scheduled to be
completed.
|
|
|
40.
|
Projects with general scope definitions are risky, because they tend to expand
gradually, without specific authorization, in a process called ____________________.
|
|
|
41.
|
According to the concept called ____________________, adding manpower to a late
software project only makes it later.
|
Matching
|
|
|
Identify the letter of the choice that best matches the phrase or
definition. a. | project management | f. | weight | b. | project
coordinator | g. | bottom-up
technique | c. | project leader | h. | dependent | d. | milestone | i. | concurrent | e. | constraint | j. | predecessor |
|
|
|
42.
|
Usually a senior systems analyst or an IT department manager, if the project is
large.
|
|
|
43.
|
A condition, restriction, or requirement that the system must satisfy.
|
|
|
44.
|
The process of planning, scheduling, monitoring, and reporting upon the
development of an information system.
|
|
|
45.
|
Handles the administrative responsibilities for the development team.
|
|
|
46.
|
An importance value assigned to an estimate.
|
|
|
47.
|
The kind of tasks that must be completed one after another.
|
|
|
48.
|
A recognizable reference point that can be used to monitor progress and manage
the project.
|
|
|
49.
|
Tasks that can start at the same time are this kind of task.
|
|
|
50.
|
The kind of task upon which other tasks depend.
|